Monday 20 January 2020

Time And Work  (Notes)

Time= Work done/Efficiency
  • When work is same.
 Time∝1/Efficiency
  • If A can do a piece of work in n days.
                                               Then, per day working efficiency of A = 1/n
  • If working efficiency of A & B is → x : y.
Then, the time taken by A & B to finish the work is in the ratio → y : x
                e.g. If A does three times faster work than ‘B’, then ratio of work done by A and B is 3 : 1.
                Then
                   Ratio of time taken by A & B = 1 : 3
  • If A can do a piece of work is x days and B can do a piece of work in y days, then both of them working together will do the same work in
xy/(x+y)  days
Explanation 
⇒ A’s 1 day’s work = 1/x
B’s 1 day’s work = 1/y
(A + B)’s 1 day work = 1/x+1/y =(x + y)/xy
A + B will complete the work in = xy/(x + y)
Q. A can finish a piece of work by working alone in 6 days and B, while working alone, can finish the same work in 12 days. If both of them work together, then in how many days, the work will be finished? 
Sol.  x = 6, y = 12
Working together A + B will complete the work in = xy/(x + y)=(6 × 8)/18
= 4 days


  • If A, B & C will working alone, can complete a work in x, y and z days, respectively, then they will together complete the work in
xyz/(xy+yz+zx)
Explanation
⇒ A’s 1 day work = 1/x
B’s 1 day work = 1/y
C’s 1 day work = 1/z
(A + B + C)’s 1 day work = 1/x+1/y+1/z  =(yz+xz+xy)/xyz
(A + B + C) will complete the work in
=xyz/(yz+xz+xy)

Q. A, B, and C can complete a piece of work in 10, 15 and 18 days, respectively. In how many days would all of them complete the same work working together?
Sol. x = 10 days, y = 15 days & z = 18 days
The work will be completed in
=(10×15×18)/(10×15+15×18+18×10)
=2700/600=4½  days
  • Two persons A & B, working together, can complete a piece of work in x days. If A, working alone, can complete the work in y days, then B, working alone, will complete the work in
⇒xy/(y-x)
Explanation 
⇒ A + B’s 1 day work = 1/x
A’s 1-day work = 1/y
B’s 1 day work = 1/x-1/y
=(y-x)/yx
B will complete the work = yx/(y – x)

Q. A and B working together take 15 days to complete a piece of work. If A alone can do this work in 20 days, how long would B take to complete the same work?
Sol. x = 15, y = 20
B will complete the work in = (15 × 20)/5
= 60 days

Click Here to Attempt More Questions From Quantitative Aptitude For SSC CGL 

  • If A & B working together, can finish a piece of work is x days, B & C in y days, C & A in z days. Then, A + B + C working together will finish the job is
⇒2xyz/(xy+yz+zx)
Explanation
⇒ A + B’s 1 day work = 1/x
B + C’s 1 day work = 1/y
C + A’s 1 day work = 1/z
[(A + B) + (B + C) + (C + A)]’s 1 day’s work
=1/x+1/y+1/z
=(yz+xz+xy)/xyz
2 (A + B + C)’s 1 day work = (xy + yz + xz)/xyz
A + B + C’s 1 day work = (xy + yz + xz)/2xyz
A + B + C working together will complete the work in
=2xyz/(xy+yz+xz)

Q. A and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days. How long would they take to complete the full work together?
Sol. x = 12 days, y = 15 days, z = 20 days
A+B+C=(2×12×15×20)/(180+300+240)
=7200/720=10 days
  • If A can finish a work in x days and B is k times efficient than A, then the time taken by both A and B, working together to complete the work is
x/(1+k)
Explanation
⇒ Ratio of working efficiency, A & B = 1 : k
Ratio of Time taken = k : 1
k → x days
1r → x/k days
A → x days
B → x/k days
1 day work of A = 1/x
1 day work of B = k/x days
(A + B)’s 1 day work = 1/x+k/x=(k + 1)/x
(A + B) will complete the work is = x/(k+1)

Q. Harbans Lal can do a piece of work in 24 days. If Bansi Lal works twice as fast as Harbans Lal, how long would they take to finish the work working together?
Sol. x = 24, k = 2
Working together they will complete the work in = 24/(1 + 2)
=24/3=8 days

No comments:

Post a Comment